Production Timeline


Amber Mills – Production Schedule

Filming – May 24 to June 3

Tracking – June 4 – June 10

Modelling Assets - June 10 – June 24
Lizard
Egg
Egg cup

Rigging – June 25 - July 2
Lizard will be doing simple squirmy movements, but will require almost full rigging.

Animation – July 3 to July 9

Dynamics – July 9 to July 23
Egg shell particle effects

Lighting and Rendering - July 24 – July 31

Compositing -  Aug 1 to Aug 14
Rotoscoping and tracking
Colour correction
Surprises